Fold in Ballygall Road East

Just brief update on Ballygall Road East as Fold Ireland propose to
publish the planning notice in tomorrows newspapers. We have met all
of the remaining residents so they are all aware of the plan.

We have 10 residents left to move from the 4 blocks that are in phase
1 we would hope to have most of these moved before Christmas.

I have received the schedule below from Fold Ireland and all going
well they hope to be on site in March of this year.

· Erect Site sign on site Friday 26 October 2012

· Planning can then be lodged 2 weeks after this date 12th November 2012

· Building regulation application will be lodged in November
after the Planning has be submit

· Objections must be lodged with DCC within 5 weeks of
lodgement of Planning to be valid 17/12/12

· The Planning Office is expected to offer a decision within 8
weeks 31/12/12

· If no objections then planning should be granted by 31/12/12

· An appeal to An Bord Pleanala can be made with 4 weeks of a
Decision by DCC

· All being well we could commence on site any time after the
stand still period 28th January 2013

If you need any further information give me a call

Brian Byrne |Housing Manager|

Ceantar an Iarthuaiscirt | Ionad Cathartha Fhionnghlaise | Bóthar Uí
Mhaoilíosa | Baile Átha Cliath |

North West Area|Finglas Civic Centre|Mellowes Road|Dublin 11|

‘: +353 1 222 5410 | 7: +353 1 8567016|
* : brian.byrne@dublincity.ie